Kansas Retainage Statutes
Getting informed about prompt payment laws is important. An examination of Kansas’ retainage laws, the rules and regulations related to the amount and timing of allowable retained payments, is important to know your rights and responsibilities as a party on a construction project. Kansas’ specific laws can be found in: K.S.A. 16-1904(a), K.S.A. 16-1904(d) and (e), K.S.A. 16-1904(h) – (j), and K.S.A. 68-411, and are reproduced below.
[hr]
[toc=”2,3,4″ title=”Table of contents”]
Retainage Statute on Private Projects
N/A
Retainage Statute on Public Projects
16-1904(a):
Retainage shall not exceed 5% of the value of the contract or subcontract unless the owner or contractor determines that a higher rate of retainage is required to ensure performance of the contract. Retainage, however, shall not exceed 10% of the value of the contract or subcontract.
16-1904(d):
A contractor may withhold not more than 150% of the value of incomplete work, provided that the incomplete work is due to the fault of a subcontractor. Any amounts retained for incomplete work shall be paid within 45 days after completion of the work as part of the regular payment cycle.
16-1904(e):
A subcontractor may withhold not more than 150% of the value of incomplete work that is the responsibility of another subcontractor, provided that the incomplete work is due to the fault of such other subcontractor. Any amounts retained for incomplete work shall be paid within 45 days after completion of the work as a part of the regular payment cycle.
16-1904(h):
An owner, contractor or subcontractor must release all remaining retainage on any undisputed payment due on a construction project within 30 days after substantial completion of the project as part of the regular payment cycle; however, if any contractor or subcontractor is still performing work on the project, an owner may withhold that portion of the retainage attributable to such work until 30 days after such work is completed.
16-1904(i):
If an owner, contractor or subcontractor fails to pay retainage, if any, pursuant to the terms of a contract for public construction or as required by this act, the owner, contractor or subcontractor shall pay interest to the contractor or subcontractor to whom payment was due, beginning on the first business day after the payment was due, at a rate of 18% per annum.
16-1904(j):
Nothing in this section shall prevent early release of retainage if it is determined by the owner, the contractor and the project architect or engineer, that a subcontractor has completed performance satisfactorily and that the subcontractor can be released prior to substantial completion of the entire project without risk or additional cost to the owner or contractor. Once so determined, the contractor shall request such adjustment in retainage, if any, from the owner as necessary to enable the contractor to pay the subcontractor in full, and the owner shall, as part of the next contractual payment cycle, release the subcontractor’s retainage to the contractor, who shall, as part of the next contractual payment cycle, release such retainage as is due to the subcontractor.
68-411:
The secretary of transportation shall make partial payment to a contractor performing any road or bridge work under contract with it, as the work may progress, said partial payment not to be less than ninety percent (90%) of the contract price of the material delivered and work done and accepted. The secretary shall provide by regulation, to be made a part of all specifications, for the withholding of not more than ten percent (10%) of the full contract price of any such work until the work is satisfactorily completed and approved by the secretary and the provisions of the contract and bond therefor have been fully satisfied.
Leave a Reply