I'M IN THE STATE OF CALIFORNIA AND LICENCES C-8 CONTRACTOR. I INVOICED FINAL ALMOST 3 MONTHS AGO AND STILL HAVE NOT RECEIVED PAYMENT. THIS IS NOT INCLUDING RETENTION. THE PROJECT STILL HAS TO GET FINAL INSPECTIONS. SHOULD I FILE A LIEN AT THIS POINT.