On the Georgia lien waivers, there is language that says "WHEN YOU EXECUTE AND SUBMIT THIS DOCUMENT, YOU SHALL BE CONCLUSIVELY DEEMED TO HAVE BEEN PAID IN FULL THE AMOUNT STATED ABOVE, EVEN IF YOU HAVE NOT ACTUALLY RECEIVED SUCH PAYMENT, 60 DAYS AFTER THE DATE STATED ABOVE UNLESS YOU FILE EITHER AN AFFIDAVIT OF NONPAYMENT OR A CLAIM OF LIEN PRIOR TO THE EXPIRATION OF SUCH 60 DAY PERIOD." If we signed Interim Waivers and Release Upon Payment and we aren't paid, does that mean we need to file a lien for each progress waiver? What if the 60 days expire but my last furnishing date was less than 90 days ago so I'm still within my lien rights timeline?