North Carolina Bond Claim Guide and FAQs

File Your North Carolina Bond Claim & Get Paid!

File A Bond Claim Now
North-Carolina-Bond-Claims

North Carolina Bond Claim Overview

North Carolina

Preliminary Notice Deadlines
Contractor's Project Statement provided to subcontractors.

North Carolina

Bond Claim Deadlines
Prime contractors cannot file a claim against their own bond.

North Carolina

Preliminary Notice Deadlines
75 Days

At least sub-subs and maybe subs, must provide a Notice of Public Subcontract within 75 days of first furnishing labor and/or materials.

North Carolina

Bond Claim Deadlines
120 Days

For those who did not contract with the prime, must file a bond claim with the prime contractor within 120 days of last furnishing labor or materials to the project (good practice for those who did contract with prime as well). Enforcement lawsuit must be filed within "longer period of one year from the day on which the last of the labor was performed or material was furnished by the claimant, or one year from the day on which final settlement was made with the contractor.”

North Carolina

Preliminary Notice Deadlines
75 Days

At least parties with no contract with the GC, (and maybe them, too) must provide a Notice of Public Subcontract within 75 days of first furnishing labor and/or materials.

North Carolina

Bond Claim Deadlines
120 Days

For those who did not contract with the prime, must file a bond claim with the prime contractor within 120 days of last furnishing labor or materials to the project (good practice for those who did contract with prime as well). Enforcement lawsuit must be filed within "longer period of one year from the day on which the last of the labor was performed or material was furnished by the claimant, or one year from the day on which final settlement was made with the contractor.”

North Carolina Bond Claim FAQs

Claim FAQs

Who is protected under North Carolina Bond Claim Laws?

In North Carolina, a furnisher of labor or materials to a public project below the general contractor may file a bond claim upon non-payment. Parties in contract with the general contractor, subcontractor, or sub-subcontractor are specifically protected – parties beyond that tier may be covered, but it is not specifically outlined by the statute.

Summary
North Carolina Bond Claim FAQs
Article Name
North Carolina Bond Claim FAQs
Description
Summary of North Carolina bond claim and notice laws and requirements for private North Carolina projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

When is the deadline to file a North Carolina Bond Claim?

Bond Claim: A bond claim must be received by the general contractor within 120 days of the claimant’s last furnishing labor and/or materials to the project.

Lien on Contract Funds Held by Contractor if No Proper Bond: Same as for regular mechanic’s lien on a private work of improvement.

Summary
North Carolina Bond Claim FAQs
Article Name
North Carolina Bond Claim FAQs
Description
Summary of North Carolina bond claim and notice laws and requirements for private North Carolina projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Who should receive the North Carolina Bond Claim?

Bond Claim: The only party specifically required by statute to receive the bond claim is the general contractor. It may be advisable to also send a copy of the bond claim to the contracting public entity and the surety, if known.

Lien on Contract Funds Held by Contractor if No Proper Bond: Same as for regular mechanic’s lien on a private work of improvement.

Summary
North Carolina Bond Claim FAQs
Article Name
North Carolina Bond Claim FAQs
Description
Summary of North Carolina bond claim and notice laws and requirements for private North Carolina projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

When is the deadline to initiate suit, or, how long is my North Carolina Bond Claim effective?

Bond Claim: An suit to enforce the bond claim must be initiated more than 90 days, but less than 1 year after last furnishing of labor and/or materials by the claimant or 1 year from the date of final settlement with the general contractor.

Lien on Contract Funds Held by Contractor if No Proper Bond: Same as for regular mechanic’s lien on a private work of improvement.

Summary
North Carolina Bond Claim FAQs
Article Name
North Carolina Bond Claim FAQs
Description
Summary of North Carolina bond claim and notice laws and requirements for private North Carolina projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

What must the North Carolina Bond Claim include?

Bond Claim: The bond claim must include the following information, 1) the amount claimed; 2) the name of the party to whom the labor and/or materials were furnished. It may also be advisable to include some description of the project, and to identify the public entity, the general contractor, and the labor and/or material furnished.

Lien on Contract Funds Held by Contractor if No Proper Bond: Same as for regular mechanic’s lien on a private work of improvement.

Summary
North Carolina Bond Claim FAQs
Article Name
North Carolina Bond Claim FAQs
Description
Summary of North Carolina bond claim and notice laws and requirements for private North Carolina projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

What are the Lien Waiver Rules?

North Carolina does not have statutory lien waiver forms, and therefore, you can use any lien waiver forms. Since lien waivers are unregulated, be careful when reviewing and signing lien waivers. See this article: Should You Sign That Lien Waiver?.

Also, North Carolina state law prohibits contractors and suppliers from waiving their right to file a mechanics lien in contract. You can learn more about the prohibition of such “no lien clauses” at this article: Where Can You Waive Your Lien Rights Before Payment?

Summary
North Carolina Bond Claim FAQs
Article Name
North Carolina Bond Claim FAQs
Description
Summary of North Carolina bond claim and notice laws and requirements for private North Carolina projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Can suppliers to suppliers file Bond Claims?

Maybe. Suppliers to suppliers may be able to file a bond claim in North Carolina. The law is not clear.

Summary
North Carolina Bond Claim FAQs
Article Name
North Carolina Bond Claim FAQs
Description
Summary of North Carolina bond claim and notice laws and requirements for private North Carolina projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

How must the North Carolina Bond Claim be sent?

Bond Claim: The bond claim must be sent to the general contractor’s office via registered or certified mail, or by personal service.

Lien on Contract Funds Held by Contractor if No Proper Bond: Must be served on the recipient via personal service, delivery service, or certified mail return receipt requested. Proof of service is necessary, and it seems that actual service appears essential.

Summary
North Carolina Bond Claim FAQs
Article Name
North Carolina Bond Claim FAQs
Description
Summary of North Carolina bond claim and notice laws and requirements for private North Carolina projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Need More Help with North Carolina Bond Claims? We're Here.

Ask an expert for free

Check out our payment experts
Construction attorneys: Courtney Stricklen, Christopher Ng, Andrea Goldman, and Peter Ryan

Recent Questions & Answers About North Carolina Claims

How do I protect myself on a Public works project?

I began a state/county project on March 2, 2020. The GC has changed the scope of work several times and I am beginning to experience payment problems. I want to make sure I am doing everything possible to protect myself. I sent a Notice of Public Subcontract to the GC, but is there anything else I...

I'm a Masonry Subcontractor I would like to place a lien against Home 2 Suites in Asheville NC.

I'm a Masonry Subcontractor the project was completed 11/2018 we received our lien Waver for last payment and change order on the 1/2019 and we still have not received payments. the Hotel has been open for a year. What can we do to receive our payment?

how do I renew part ownership of a construction company that I am part of and help build?

I am a construction worker with my Grandfather years ago in a company he made me part owner of, since then my Grandfather died and his children has been harassing me on nukes that I don't keep around my construction site,how do I take my legal right as owner and co-owner of the construction company...

How to file a lien in North Carolina

Need to file a North Carolina mechanics lien? File your mechanics lien with Levelset, the lien experts quickly and easily. Or you can follow the 3 steps below to file a lien yourself with Levelset’s free information.
Step 2
Download your North Carolina Mechanics Lien Form
Step 3 Find your North Carolina County Recorder
See all North Carolina Counties
File with the Mechanics Lien Experts
Product screenshot suggesting a found material supplier on a project details screen.
We’re the Mechanics Lien experts. With us it’s fast, easy, affordable, and done right!
File Now

Want to Learn More about How North Carolina Contractors Pay?
Progress Residential
Rating 5.0
D.R. Horton
Rating 5.0
SteelFab Inc
Rating 5.0
Core & Main
Rating 5.0
See other Lists of Contractors and How to Best Work With Them

North Carolina Bond Claim Free Forms

Notice of Intent to Make Bond Claim Form

Notice of Intent to Make Bond Claim Form

A Notice of Intent to Make Bond Claim is not a required document, but it can be a powerful one. By sending this notice, a claimant...

Get Form Now

North Carolina Bond Claim Statutes

When you perform work on a state construction project in North Carolina, and are not paid, you can file a “lien” against the project pursuant to North Carolina’s Little Miller Act. Since the claim is not against the state or county’s actual property, but instead against a posted bond, the claim is not really called a “lien” but is more frequently referred to as a “bond claim” or “little miller act claim.” North Carolina’s Little Miller Act is found in North Carolina General Statutes chapter 44A, Article 3, and is reproduced below. Updated as of 2020.

North Carolina Little Miller Act: Article 3- Model Payment and Performance Bond

§ 44A‑25. Definitions.

Unless the context otherwise requires in this Article:

(1) “Claimant” includes any individual, firm, partnership, association or corporation entitled to maintain an action on a bond described in this Article and shall include the “contracting body” in a suit to enforce the performance bond.

(2) “Construction contract” means any contract for the construction, reconstruction, alteration or repair of any public building or other public work or public improvement, including highways.

(3) “Contracting body” means any department, agency, or political subdivision of the State of North Carolina which has authority to enter into construction contracts.

(4) “Contractor” means any person who has entered into a construction contract with a contracting body.

(5) “Labor or materials” shall include all materials furnished or labor performed in the prosecution of the work called for by the construction contract regardless of whether or not the labor or materials enter into or become a component part of the public improvement, and further shall include gas, power, light, heat, oil, gasoline, telephone services and rental of equipment or the reasonable value of the use of equipment directly utilized in the performance of the work called for in the construction contract.

(6) “Subcontractor” means any person who has contracted to furnish labor or materials to, or who has performed labor for, a contractor or another subcontractor in connection with a construction contract.

Summary
North Carolina Bond Claim FAQs
Article Name
North Carolina Bond Claim FAQs
Description
Summary of North Carolina bond claim and notice laws and requirements for private North Carolina projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 44A‑26. Bonds required.

(a) When the total amount of construction contracts awarded for any one project exceeds three hundred thousand dollars ($300,000), a performance and payment bond as set forth in (1) and (2) is required by the contracting body from any contractor or construction manager at risk with a contract more than fifty thousand dollars ($50,000); provided that, for State departments, State agencies, and The University of North Carolina and its constituent institutions, a performance and payment bond is required in accordance with this subsection if the total amount of construction contracts awarded for any one project exceeds five hundred thousand dollars ($500,000). In the discretion of the contracting body, a performance and payment bond may be required on any construction contract as follows:

(1) A performance bond in the amount of one hundred percent (100%) of the construction contract amount, conditioned upon the faithful performance of the contract in accordance with the plans, specifications and conditions of the contract. Such bond shall be solely for the protection of the contracting body that is constructing the project.

(2) A payment bond in the amount of one hundred percent (100%) of the construction contract amount, conditioned upon the prompt payment for all labor or materials for which a contractor or subcontractor is liable. The payment bond shall be solely for the protection of the persons furnishing materials or performing labor for which a contractor, subcontractor, or construction manager at risk is liable.

(b) The performance bond and the payment bond shall be executed by one or more surety companies legally authorized to do business in the State of North Carolina and shall become effective upon the awarding of the construction contract.

Summary
North Carolina Bond Claim FAQs
Article Name
North Carolina Bond Claim FAQs
Description
Summary of North Carolina bond claim and notice laws and requirements for private North Carolina projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 44A‑27. Actions on payment bonds; service of notice.

(a) Subject to the provision of subsection (b) hereof, any claimant who has performed labor or furnished materials in the prosecution of the work required by any contract for which a payment bond has been given pursuant to the provisions of this Article, and who has not been paid in full therefor before the expiration of 90 days after the day on which the claimant performed the last such labor or furnished the last such materials for which he claims payment, may bring an action on such payment bond in his own name, to recover any amount due him for such labor or materials and may prosecute such action to final judgment and have execution on the judgment.

(b) Any claimant who has a direct contractual relationship with any subcontractor but has no contractual relationship, express or implied, with the contractor may bring an action on the payment bond only if he has given written notice of claim on payment bond to the contractor within 120 days from the date on which the claimant performed the last of the labor or furnished the last of the materials for which he claims payment, stating with substantial accuracy the amount claimed and the name of the person for whom the work was performed or to whom the material was furnished. The contractor shall, in response to a written request served by any claimant in accordance with the provisions of subsection (c) of this section, send a copy of the payment bond required by this Article to the claimant making the request within seven calendar days after receipt of such request. Subject to the exception set forth in subsection (e) of this section, unless the contractor has failed to satisfy its obligation to timely furnish a copy of the payment bond to a claimant upon proper request by the claimant, the claim of such a claimant shall not include labor or materials provided more than 75 days prior to the claimant’s service, in accordance with subsections (c) and (d) of this section, of its written notice of public subcontract to the contractor.

(c) The notices required by and any requests for copy of payment bond referenced by subsection (b) of this section, shall be served by certified mail, or by signature confirmation as provided by the United States Postal Service, postage prepaid, in an envelope addressed to such contractor at any place where his office is regularly maintained for the transaction of business or to such agent identified in the contractor’s project statement referenced in subdivision (1) of subsection (f) of this section or served in any manner provided by law for the service of summons.

(d) The form of the notice of public subcontract to be served pursuant to subsection (b) of this section shall be substantially as follows:

“NOTICE OF PUBLIC SUBCONTRACT

(1) Name and address of the subcontractor giving notice of public subcontract:

(2) General description of the real property on which the labor was or is to be performed or the material was or is to be furnished (street address, tax map lot and block number, reference to recorded instrument, or any description that reasonably identifies the real property):

(3) General description of the subcontractor’s contract, including the names and addresses of the parties thereto:

(4) General description of the labor and material performed and furnished thereunder:

Dated: _______________

____________________________________

Subcontractor”

(e) Notwithstanding subsections (b), (c), and (d) of this section, the obligation to provide a notice of public subcontract shall not apply to claims of twenty thousand dollars ($20,000) or less and, for any claim exceeding twenty thousand dollars ($20,000), shall apply only to that portion of the claim in excess of twenty thousand dollars ($20,000).

(f) In connection with any construction contract for which a bond is required by G.S. 44A-26(a), all of the following shall apply:

(1) The contractor shall provide to each subcontractor that it engages to perform labor or furnish materials in the performance of the construction contract a contractor’s project statement containing all of the following information:

a. The name of the project.

b. The physical address of the project.

c. The name of the contracting body.

d. The name of the contractor.

e. The name, phone number, and mailing address of an agent authorized by the contractor to accept service of the requests for payment bond, the notice of public subcontract, and the notice of claim on payment bond referenced in subsection (b) of this section.

f. The name and address of the principal place of business of the surety issuing the payment bond required by G.S. 44A-26(a) for the construction contract.

(2) Each subcontractor shall provide each subcontractor that it engages to perform labor or furnish materials in the performance of the construction contract a copy of the contractor’s project statement.

(3) No agreement entered into between a contractor and a subcontractor or between a subcontractor and its subcontractor shall be enforceable against the lower tier party until the contractor’s project statement has been provided to the lower tier party.

Summary
North Carolina Bond Claim FAQs
Article Name
North Carolina Bond Claim FAQs
Description
Summary of North Carolina bond claim and notice laws and requirements for private North Carolina projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 44A‑28. Actions on payment bonds; venue and limitations.

(a) Every action on a payment bond as provided in G.S. 44A-27 shall be brought in a court of appropriate jurisdiction in a county where the construction contract or any part thereof is to be or has been performed.

(b) No action on a payment bond shall be commenced after the expiration of the longer period of one year from the day on which the last of the labor was performed or material was furnished by the claimant, or one year from the day on which final settlement was made with the contractor.

Summary
North Carolina Bond Claim FAQs
Article Name
North Carolina Bond Claim FAQs
Description
Summary of North Carolina bond claim and notice laws and requirements for private North Carolina projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 44A‑29. Limitation of liability of a surety.

No surety shall be liable under a payment bond for a total amount greater than the face amount of the payment bond. A judgment against any surety may be reduced or set aside upon motion by the surety and a showing that the total amount of claims paid and judgments previously rendered under such payment bond, together with the amount of the judgment to be reduced or set aside, exceeds the face amount of the bond.

Summary
North Carolina Bond Claim FAQs
Article Name
North Carolina Bond Claim FAQs
Description
Summary of North Carolina bond claim and notice laws and requirements for private North Carolina projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 44A‑30. Variance of liability; contents of bond.

(a) No act of or agreement between a contracting body, a contractor or a surety shall reduce the period of time for giving notice under G.S. 44A‑27(b) or commencing action under G.S. 44A‑28(b) or otherwise reduce or limit the liability of the contractor or surety as prescribed in this Article.

(b) Every bond given by a contractor to a contracting body pursuant to this Article shall be conclusively presumed to have been given in accordance herewith, whether or not such bond be so drawn as to conform to this Article. This Article shall be conclusively presumed to have been written into every bond given pursuant thereto.

Summary
North Carolina Bond Claim FAQs
Article Name
North Carolina Bond Claim FAQs
Description
Summary of North Carolina bond claim and notice laws and requirements for private North Carolina projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 44A‑31. Certified copy of bond and contract.

(a) Any person entitled to bring an action or any defendant in an action on a payment bond shall have a right to require the contracting body to certify and furnish a copy of the payment bond and of the construction contract covered by the bond. It shall be the duty of such contracting body to give any such person a certified copy of the payment bond and the construction contract upon not less than 10 days’ notice and request. The contracting body may require a reasonable payment for the actual cost of furnishing the certified copy.

(b) A copy of any payment bond and of the construction contract covered by the bond certified by the contracting body shall constitute prima facie evidence of the contents, execution and delivery of such bond and construction contract.

Summary
North Carolina Bond Claim FAQs
Article Name
North Carolina Bond Claim FAQs
Description
Summary of North Carolina bond claim and notice laws and requirements for private North Carolina projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 44A‑32. Designation of official; violation a misdemeanor.

Each contracting body shall designate an official thereof to require the bonds described by this Article. If the official so designated shall fail to require said bond, he shall be guilty of a Class 1 misdemeanor.

Summary
North Carolina Bond Claim FAQs
Article Name
North Carolina Bond Claim FAQs
Description
Summary of North Carolina bond claim and notice laws and requirements for private North Carolina projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 44A‑33. Form.

(a) A performance bond form containing the following provisions shall comply with this Article: the date the bond is executed; the name of the principal; the name of the surety; the name of the contracting body; the amount of the bond; the contract number; and the following conditions:

“KNOW ALL MEN BY THESE PRESENTS, That we, the PRINCIPAL AND SURETY above named, are held and firmly bound unto the above named Contracting Body, hereinafter called the Contracting Body, in the penal sum of the amount stated above for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, and successors, jointly and severally, firmly by these presents.

“THE CONDITION OF THIS OBLIGATION IS SUCH, that whereas the Principal entered into a certain contract with the Contracting Body, numbered as shown above and hereto attached:

“NOW THEREFORE, if the Principal shall well and truly perform and fulfill all the undertakings, covenants, terms, conditions, and agreements of said contract during the original term of said contract and any extensions thereof that may be granted by the Contracting Body, with or without notice to the Surety, and during the life of any guaranty required under the contract, and shall also well and truly perform and fulfill all the undertakings, covenants, terms, conditions, and agreements of any and all duly authorized modifications of said contract that may hereafter be made, notice of which modifications to the Surety being hereby waived, then, this obligation to be void; otherwise to remain in full force and virtue.

“IN WITNESS WHEREOF, the above-bounden parties have executed this instrument under their several seals on the date indicated above, the name and corporate seal of each corporate party being hereto affixed and these presents duly signed by its undersigned representative, pursuant to authority of its governing body.”

Appropriate places for execution by the surety and principal shall be provided.

(b) A payment bond form containing the following provisions shall comply with this Article: the date the bond is executed; the name of the principal; the name of the surety; the name of the contracting body; the contract number; and the following conditions:

“KNOW ALL MEN BY THESE PRESENTS, That we, the PRINCIPAL and SURETY above named, are held and firmly bound unto the above named Contracting Body, hereinafter called the Contracting Body, in the penal sum of the amount stated above, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, and successors, jointly and severally, firmly by these presents.

“THE CONDITION OF THIS OBLIGATION IS SUCH, that whereas the Principal entered into a certain contract with the Contracting Body, numbered as shown above and hereto attached;

“NOW THEREFORE, if the Principal shall promptly make payment to all persons supplying labor and material in the prosecution of the work provided for in said contract, and any and all duly authorized modifications of said contract that may hereafter be made, notice of which modifications to the Surety being hereby waived, then this obligation to be void; otherwise to remain in full force and virtue.

“IN WITNESS WHEREOF, the above-bounden parties have executed this instrument under their several seals on the date indicated above, the name and corporate seal of each corporate party being hereto affixed and these presents duly signed by its undersigned representative, pursuant to authority of its governing body.”

Appropriate places for execution by the surety and principal shall be provided.

Summary
North Carolina Bond Claim FAQs
Article Name
North Carolina Bond Claim FAQs
Description
Summary of North Carolina bond claim and notice laws and requirements for private North Carolina projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 44A‑34. Construction of Article.

The addition of this Article shall not be construed as making the provisions of Articles 1 and 2 of Chapter 44A of the General Statutes apply to public bodies or public buildings.

Summary
North Carolina Bond Claim FAQs
Article Name
North Carolina Bond Claim FAQs
Description
Summary of North Carolina bond claim and notice laws and requirements for private North Carolina projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

§ 44A‑35. Attorneys' fees.

In any suit brought or defended under the provisions of Article 2 or Article 3 of this Chapter, the presiding judge may allow a reasonable attorneys’ fee to the attorney representing the prevailing party. This attorneys’ fee is to be taxed as part of the court costs and be payable by the losing party upon a finding that there was an unreasonable refusal by the losing party to fully resolve the matter which constituted the basis of the suit or the basis of the defense. For purposes of this section, “prevailing party” is a party plaintiff or third party plaintiff who obtains a judgment of at least fifty percent (50%) of the monetary amount sought in a claim or is a party defendant or third party defendant against whom a claim is asserted which results in a judgment of less than fifty percent (50%) of the amount sought in the claim defended. Notwithstanding the foregoing, in the event an offer of judgment is served in accordance with G.S. 1A-1, Rule 68, a “prevailing party” is an offeree who obtains judgment in an amount more favorable than the last offer or is an offeror against whom judgment is rendered in an amount less favorable than the last offer.

Summary
North Carolina Bond Claim FAQs
Article Name
North Carolina Bond Claim FAQs
Description
Summary of North Carolina bond claim and notice laws and requirements for private North Carolina projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Helping Thousands of North Carolina Contractors Like You
With Bond Claims & Getting Paid