Any person having a right to a lien who does not contract directly with the owner or contractor is required to deliver a “Notice to Contractor” within 30 days from the filing of the Notice of Commencement or 30 days following the first delivery of labor, services, or materials to the property, whichever is later.
Notice must be provided to the owner or the agent of the owner and to the contractor.