Nevada
Construction Documents

Mechanics Lien, Bond Claim, Notice and Lien Waiver Forms.


Download free Nevada Mechanics Lien and Preliminary Notice forms in PDF format. All forms are made available by zlien subject to our terms of use.

Nevada

Partial Unconditional Lien Waiver

Download

This waiver – the Unconditional Waiver and Release on Progress Payment – should be used when a progress payment on the project has been received. Further payments may be expected, but the specific partial payment discussed in the waiver has been received.

Because this is an “unconditional” waiver, it should only be used when payment has actually been received. If payment has not been received, if the check hasn’t yet cleared the bank, or if there is some other reason why payment might ultimately fail, this waiver should not be furnished. If this is the case, signing a “conditional” waiver is a safer option.

Nevada

Partial Conditional Lien Waiver

Download

This waiver – the Conditional Waiver and Release on Progress Payment – should be used when a progress payment on the project is expected. There may be future expected payments on the project, but this waiver applies only to a specific, expected progress or partial payment.

Because this is a “conditional” waiver, it is ok if payment has not yet been received. The waiver is “conditional” on the receipt of the payment and will be invalid if payment is not ultimately received. If payment has already been received in full, an “unconditional” waiver may be more appropriate.

Nevada

Final Unconditional Lien Waiver

Download

This waiver – the Unconditional Waiver and Release on Final Payment – should be used when the final payment on the project has been made and received by the party that furnished labor or materials. Signing this waiver indicates that payment has been received and no further payments are expected.

Because this is an “unconditional” waiver, it should only be used when payment has actually been received. If payment has not been received, if the check hasn’t yet cleared the bank, or if there is some other reason why payment might ultimately fail, this waiver should not be furnished. If this is the case, signing a “conditional” waiver is a safer option.

Nevada

Final Conditional Lien Waiver

Download

This waiver – the Conditional Waiver and Release on Final Payment – should be used when the final payment for a project is expected but has yet to be received. Signing this waiver signifies that no further payments are expected following the payment described in the waiver.

Because this is a “conditional” waiver, it is ok if payment has not yet been received. The waiver is “conditional” on the receipt of the payment and will be invalid if payment is not ultimately received. If payment has already been received in full, an “unconditional” waiver may be more appropriate.

Private Projects

Nevada

Notice of Right to Lien

Download

All potential lien claimants, “other than one who performs only labor,” and who do not contract directly with the property owner, must deliver a Notice of Right to Lien in order to protect lien rights. According to NRS § 108.245, the notice must be delivered within 31 days of first providing work or materials for full lien protection. (If the notice is delivered outside of the 31-day window, lien rights will protect work or materials provided in the 31 days prior to the date notice was given, and all work or materials provided afterwards until the completion of the project.) This notice must be delivered to the property owner and prime contractor.

Private Projects

Nevada

Mechanics Lien Release

Download

Private and Public construction liens and statements must be canceled once payment has been received, or for any other reasons. Lien cancellations are certificates filed with the recorder to cancel the previously filed instruments. The law requires that the lien claimant release any lien which has been satisfied within 10 days of the satisfaction.

Private Projects

Nevada

Notice of Intent to Lien

Download

On residential projects (including apartment buildings), a 15-day Notice of Intent to Lien must be sent by any party before filing a lien. On non-residential projects, it may be filed. This document advises the party that a lien will be filed if payment is not received within 15 days.

Private Projects

Nevada

208.146 Notice

Download

NRS Section 208.146 requires prime contractors to deliver a specific notice to the Property Owner and to all Subcontractors and Suppliers on a construction project. While lien rights are not affected by the failure to deliver these notices, the contractor may face disciplinary measures from the Contractor’s Board. Click the button to download a Nevada 208.146 Notice for free.

Private Projects

Nevada

Notice of Lien

Download

The construction or mechanics lien, known in Nevada as a Notice of Lien, is filed on private construction jobs when unpaid for work. Nevada also requires that the property owner (and prime contractor, if not the claimant) be served with a copy of the lien within 30 days of its filing.

Nevada

File a Bond Claim through zlien

Click Here

Bond Claims are used to collect payment on federal, state, county, and municipal construction projects. Click here to file a Bond Claim through zlien in minutes. Enter your project info, and zlien's platform will ensure that your Bond Claim is filed correctly and securely so that you get paid.

Nevada

File a Notice of Commencement through zlien

Click Here

A Notice of Commencement is available in certain states as an official means of designating the beginning of a construction project. Click below to file a Notice of Commencement through zlien.

Nevada

File a Release of Bond Claim through zlien

Click Here

When payment is received after a Bond Claim is filed, releasing the claim is sometimes required. Click here to file a Release of Bond Claim through zlien.

Nevada

File a Stop Notice through zlien

Click Here

In some states, Stop Notices are available to contractors and suppliers as an alternative to (or in addition to) their Mechanic Lien Rights. A Stop Notice is delivered to the prime contractor or property owner, and demands that they withhold enough funds to pay your claim. If the property owner or prime contractor is in possession of funds at the time your Stop Notice is sent, they will be responsible for payment of your claim if they disburse those funds to other parties. Click to file a Stop Notice through zlien.

Waiver Management. Simplified.

Stop processing waivers manually. Add organization and
accountability to your process with WaiverInboxTM by zlien.

Build A lien Waiver