State Projects
Choose Another State
![]() |
![]() |
|
![]() |
N/A | N/A |
![]() |
None | Those who did not contract with the prime contractor must file bond claim within 90 days of last furnishing labor and/or materials to the construction project, although this is a good practice for everyone. All parties must file lawsuit to enforce claim against bond within 1 year from last furnishing labor or materials. |
![]() |
None | Those who did not contract with the prime contractor must file bond claim within 90 days of last furnishing labor and/or materials to the construction project, although this is a good practice for everyone. All parties must file lawsuit to enforce claim against bond within 1 year from last furnishing labor or materials. |