State Projects
Choose Another State
![]() |
![]() |
|
![]() |
File notice of commencement within 15 days of getting the building permit, or if no permit is issued, within 15 days of beginning work. | N/A |
![]() |
Preliminary notice must be filed within 20 days from commencement of work or delivery of materials. | Claim on bond (or if no bond, on the state directly) due within 90 days from final furnishing of labor and/or materials. Action to enforce claim due within 1 year of last furnishing labor and/or materials. |
![]() |
Preliminary notice must be filed within 20 days from commencement of work or delivery of materials. | Claim on bond (or if no bond, on the state directly) due within 90 days from final furnishing of labor and/or materials. Action to enforce claim due within 1 year of last furnishing labor and/or materials. |