Private Projects

Choose Another State

notice requirements Private Projects lien requirements Private Projects
prime contractor Private Projects None. Lien must be filed w/in 180 days from when payment became due for last materials or labor provided, and enforced within 180 days from the filing date.
sub laborer Private Projects None. Lien must be filed w/in 180 days from when payment became due for last materials or labor provided, and enforced within 180 days from the filing date.
supplier other Private Projects None. Lien must be filed w/in 180 days from when payment became due for last materials or labor provided, and enforced within 180 days from the filing date.