N/A | N/A |
![]() |
None | For those who did not contract with the prime, must file a bond claim with the prime contractor within 120 days of last furnishing labor or materials to the project (good practice for those who did contract with prime as well). Enforcement lawsuit must be filed within "longer period of one year from the day on which the last of the labor was performed or material was furnished by the claimant, or one year from the day on which final settlement was made with the contractor.” |
![]() |
None | For those who did not contract with the prime, must file a bond claim with the prime contractor within 120 days of last furnishing labor or materials to the project (good practice for those who did contract with prime as well). Enforcement lawsuit must be filed within "longer period of one year from the day on which the last of the labor was performed or material was furnished by the claimant, or one year from the day on which final settlement was made with the contractor.” |