Private Projects

Choose Another State

notice requirements Private Projects lien requirements Private Projects
prime contractor Private Projects None. Lien must be filed within 120 days from project completion. Action to enforce due within 2 years from lien's filing.
sub laborer Private Projects Within 60 days of first providing labor or materials if work over $5000. Sub-Subs required to provide Notice of Intent to Lien before filing. Lien must be filed within 90 days from project completion. Action to enforce due within 2 years from lien's filing.
supplier other Private Projects Within 60 days of first providing materials if over $5000. Supplier to Sub required to provide Notice of Intent to Lien before filing. Lien must be filed within 90 days from project completion. Action to enforce due within 2 years from lien's filing.

NOTICE REQUIREMENTS

New Mexico is generally a non-notice state, meaning that notices are not required prior to the filing mechanic’s liens. However, there are some special circumstances when notice may be required.

  • Non-Residential Projects / Low Tier Subs: On non-residential projects, all parties who did not contract with the owner or original contractor must deliver a preliminary notice within 60 days of supplying labor, materials, and/or equipment to the project.    This is required only if the mechanic’s lien will be $5,000 or greater. If notice is sent late, it is effective only for services/materials provided within the previous 30 days.

THE MECHANIC’S LIEN

Prime Contractors, Subcontractors, Sub-Subs, Architects, Engineers, Surveyors, Construction Managers, Landscapers, Suppliers and Equipment Lessors all have mechanic’s lien rights in New Mexico. Suppliers to Suppliers do not have mechanic’s lien rights.    Unlicensed contractors, when required to be licensed, do not have mechanic’s lien rights.

  • Referred to as “Claim of Lien”
  • Those who contract with the owner must file liens within 120 days after completion of their contract.  All others must file liens within 90 days after substantial completion of the project.

On residential projects (4 dwelling units or less), all parties who did not contract with the property owner can file their lien…but the lien is “subject to discharge.”  Discharge is allowed if the property owner already paid funds to the original contractor before the mechanic’s lien was filed.

  • Lien expires if a lawsuit is not filed to enforce the mechanic’s lien within 2 years from the lien’s filing date.
New Mexico Resources