N/A | N/A |
![]() |
If you did not contract with the prime contractor, must serve a preliminary notice upon the prime contractor within 30 days of first furnishing labor and/or materials to the project. | If you did not contract with the prime contractor, must serve a written notice of claim to the prime contractor within 90 days of last furnishing labor and/or materials to the project. Lawsuit must be brought by any claimants against the project's bond within 1 year of last furnishing labor and/or materials. |
![]() |
If you did not contract with the prime contractor, must serve a preliminary notice upon the prime contractor within 30 days of first furnishing labor and/or materials to the project. | If you did not contract with the prime contractor, must serve a written notice of claim to the prime contractor within 90 days of last furnishing labor and/or materials to the project. Lawsuit must be brought by any claimants against the project's bond within 1 year of last furnishing labor and/or materials. |