State Projects

Choose Another State

notice requirements State Projects lien requirements State Projects
prime contractor State Projects N/A N/A
sub laborer State Projects None Must file bond claim within 4 months of last furnishing to the project. Lawsuit due within 1 year from final settlement of the public contract.
supplier other State Projects None Must file bond claim within 4 months of last furnishing to the project. Lawsuit due within 1 year from final settlement of the public contract.
Nebraska Resources