State Projects
Choose Another State
![]() |
![]() |
|
![]() |
N/A | N/A |
![]() |
None | For those who did not contract with the prime, must file a bond claim with the prime contractor and the surety within 90 days of last furnishing labor or materials to the project (good practice for those who did contract with prime as well). Enforcement lawsuit must be filed within 1 year from last furnishing labor and/or materials to the project. |
![]() |
None | For those who did not contract with the prime, must file a bond claim with the prime contractor and the surety within 90 days of last furnishing labor or materials to the project (good practice for those who did contract with prime as well). Enforcement lawsuit must be filed within 1 year from last furnishing labor and/or materials to the project. |