State Projects

Choose Another State

notice requirements State Projects lien requirements State Projects
prime contractor State Projects N/A N/A
sub laborer State Projects None Must file notice of bond claim with the prime contractor and the surety within 120 days from last furnishing labor and/or material to the project. Lawsuit to enforce the claim due within 1 year from the same last furnishing date.
supplier other State Projects None Must file notice of bond claim with the prime contractor and the surety within 120 days from last furnishing labor and/or material to the project. Lawsuit to enforce the claim due within 1 year from the same last furnishing date.