State Projects

Choose Another State

notice requirements State Projects lien requirements State Projects
prime contractor State Projects N/A N/A
sub laborer State Projects None. All tiers must bring lawsuit to enforce claim against bond within 1 year of last furnishing labor and/or materials. Those without direct contract with the prime contractor must file a Notice of Claim within 65 days from last furnishing labor and/or materials.
supplier other State Projects None, unless furnishing specially fabricated materials. If so, notice must be delivered to the prime contractor within 20 days of receiving the order for the specially fabricated materials. All tiers must bring lawsuit to enforce claim against bond within 1 year of last furnishing labor and/or materials. Those without direct contract with the prime contractor must file a Notice of Claim within 65 days from last furnishing labor and/or materials.
Massachusetts Resources




RSS Massachusetts Legal Updates