Private Projects
Choose Another State
![]() |
![]() |
|
![]() |
None. | Notice of Contract must be recorded at earlier date of (a) 60 days after filing notice of substantial completion or (b) 90 days after filing notice of termination or (c) 90 days after last furnishing labor or materials to project. Lien must be filed within earliest date of (a) 90 days after filing notice of substantial completion; (b) 120 days after filing notice of termination; (c) 120 days after last furnishing labor or materials to project. Action to enforce due within 90 days after recording lien. |
![]() |
Sub-Subs or Suppliers to subs must provide notice of identification to prime contractor within 30 days of commencing work. | Notice of Subcontract must be recorded at earlier of dates applicable to Prime, labeled to left as (a), (b) & (c). Lien must be filed within earliest date of (a) 90 days after filing notice of substantial completion; (b) 120 days after filing notice of termination; (c) 120 days after last furnishing labor or materials to project. Action to enforce due within 90 days after recording lien. |
![]() |
Sub-Subs or Suppliers to subs must provide notice of identification to prime contractor within 30 days of commencing work. | Notice of Subcontract must be recorded at earlier of dates applicable to Prime, labeled to left as (a), (b) & (c). Lien must be filed within earliest date of (a) 90 days after filing notice of substantial completion; (b) 120 days after filing notice of termination; (c) 120 days after last furnishing labor or materials to project. Action to enforce due within 90 days after recording lien. |