notice requirements Private Projects lien requirements Private Projects
prime contractor Private Projects None. Notice of Contract must be recorded at earlier date of (a) 60 days after filing notice of substantial completion or (b) 90 days after filing notice of termination or (c) 90 days after last furnishing labor or materials to project. Lien must be filed within earliest date of (a) 90 days after filing notice of substantial completion; (b) 120 days after filing notice of termination; (c) 120 days after last furnishing labor or materials to project. Action to enforce due within 90 days after recording lien.
sub laborer Private Projects Sub-Subs or Suppliers to subs must provide notice of identification to prime contractor within 30 days of commencing work. Notice of Subcontract must be recorded at earlier of dates applicable to Prime, labeled to left as (a), (b) & (c). Lien must be filed within earliest date of (a) 90 days after filing notice of substantial completion; (b) 120 days after filing notice of termination; (c) 120 days after last furnishing labor or materials to project. Action to enforce due within 90 days after recording lien.
supplier other Private Projects Sub-Subs or Suppliers to subs must provide notice of identification to prime contractor within 30 days of commencing work. Notice of Subcontract must be recorded at earlier of dates applicable to Prime, labeled to left as (a), (b) & (c). Lien must be filed within earliest date of (a) 90 days after filing notice of substantial completion; (b) 120 days after filing notice of termination; (c) 120 days after last furnishing labor or materials to project. Action to enforce due within 90 days after recording lien.
Massachusetts Resources




RSS Massachusetts Legal Updates