State Projects
Choose Another State
![]() |
![]() |
|
![]() |
N/A | N/A |
![]() |
None | Must file bond claim within 60 days from last furnishing labor and/or material to the project. Must file lawsuit: (i) On general state owned properties within 1 year from the project's substantial completion; (ii) On state university and other state projects, within 60 days from the project's substantial completion; and (iii) On Department of Transportation projects, within 90 days of receiving a notice of rejection of claim. |
![]() |
None | Must file bond claim within 60 days from last furnishing labor and/or material to the project. Must file lawsuit: (i) On general state owned properties within 1 year from the project's substantial completion; (ii) On state university and other state projects, within 60 days from the project's substantial completion; and (iii) On Department of Transportation projects, within 90 days of receiving a notice of rejection of claim. |