notice requirements Private Projects lien requirements Private Projects
prime contractor Private Projects None. Must be filed within 45 days after completion of work. Court will hold a hearing to determine if probable cause exists for the lien within 3-10 days after service, and if found, will attach. Must enforce lien within 3 months after attachment.
sub laborer Private Projects None. Must be filed within 45 days after completion of work. Court will hold a hearing to determine if probable cause exists for the lien within 3-10 days after service, and if found, will attach. Must enforce lien within 3 months after attachment.
supplier other Private Projects None. Must be filed within 45 days after completion of work. Court will hold a hearing to determine if probable cause exists for the lien within 3-10 days after service, and if found, will attach. Must enforce lien within 3 months after attachment.