Virginia’s Interesting 150 Day Rule

In most states, a contractor only has 1 lien deadline of concern:  when the lien must be filed.  In Virginia, however, contractors must juggle two lien deadlines.

First, like other states, Virginia has a regular lien filing time requirement.  All liens must be filed within 90 days from when labor and services were last performed by the contractor.

Unlike other states, however, Virginia has an interesting second deadline, referred to in the state as the “150 day rule.”

From the last day of work, the claimant must count backwards 150 days.   Generally speaking, a contractor is not allowed to include any labor or materials supplied outside this window in its mechanics lien.

While the 150-day rule does not apply to retainage funds or sums not yet due because of a “pay when paid” clause, it usually applies otherwise, and will invalidate a lien if it includes sums due not within this 150-day window.

As mentioned in a previous post about the “payment chain” in Virginia,  an arguable third deadline of concern in that state, subcontractors and suppliers in Virginia have extra motivation for filing liens immediately upon non-payment.   The 150-day rule in Virginia is even further cause.

Virginias Interesting 150 Day RuleDid you enjoy this article?
Virginias Interesting 150 Day Rule
Share
the
Love
Get Free Updates

, , , , , , , ,

About Scott Wolfe Jr

Scott Wolfe Jr. is the CEO of Zlien, a company that provides software and services to help building material supply and construction companies reduce their credit risk and default receivables through the management of mechanics lien and bond claim compliance. He is also the founding author of the Lien Blog, a leading online publication about liens, security instruments and getting paid on every account. Scott is a licensed attorney in six states with extensive experience in corporate credit management and collections law, with a specific emphasis on utilizing mechanic liens, UCC filings and other security instruments to protect and manage receivables. You can connect with him via Twitter, LinkedIn and Google+.Read Scott's Biography Post Here

One Pingback/Trackback

  • http://constructionlawva.blogspot.com Chris Hill

    Great post! Just to clarify the 150 day lookback is from the date of lien or last day of work whichever is later. So if the project takes less than 150 days you can catch it all.
    Thanks Scott

  • Pingback: Don't Forget The 150-Day Rule In Virginia