- zlien - http://www.zlien.com -

Five Things To Know About Florida’s Mechanic Lien Laws

Posted By Scott Wolfe Jr On January 4, 2012 @ 10:33 am In Construction Finance | 61 Comments

Five Things To Know About Floridas Mechanic Lien Laws

One of the most popular posts on this blog has been an article I wrote in December 2009 titled: 5 Things To Know About The Miller Act. It’s been a long time since we discussed mechanics lien law in Florida, and so I’m inspired to write a top five post about Florida’s mechanics lien laws.

Parties looking to file a mechanics lien in Florida must comply with the statutes housed in Title 40, Chapter 713, Part I of the Florida Statutes, titled the “Construction Lien Law.”  Here are the top five things you should know about these laws to preserve, perfect and enforce your mechanics lien rights.

1) Preliminary Notice is Required

If you don’t deliver a preliminary notice at the start of furnishing labor or materials, you will likely lose your mechanics lien rights in Florida. All parties who did not contract directly with the property owner must serve a Notice to Owner within 45 days of furnishing labor and/or materials to the construction project. There are only two small exceptions to this requirement, as the requirement does not exist for pure individual laborers or for professionals (i.e. architects, engineers, etc.).

The preliminary notice must contain all the information required by the statute (including a statutory WARNING statement), and must be sent to certain parties.  Specifically, make sure you send the preliminary notice to those listed in any filed Notice of Commencement, and:

  • If hired by the general contractor, send the notice to the property owner;
  • If hired by a subcontractor, send the notice to the property owner and the general contractor; or
  • If hired by a sub-subcontractor, send the notice to the property owner, the general contractor and the subcontractor.

Five Things To Know About Floridas Mechanic Lien Laws

2) You Must File A Florida Mechanics Lien Within 90 Days From Last Doing Work (Warranty Work Not Included)

In some states, the lien deadline starts to count from the end of the entire construction project.  Not so in Florida.  Claimants in Florida must record their mechanics lien within 90 days from last furnishing labor, services or materials to a construction project.  The 90 day period starts to count when the substantive portion of your work is completed, and you cannot include the correction of deficiencies in work or warranty work when determining this date.  If you are an equipment rental company, the last date of furnishing is the last date the equipment was actually on site and available to the parties for use.

When recording your mechanics lien, be careful where you are recording.  While most counties maintain county property records with the Clerk of Court for the Florida county, there are some exceptional counties where the property records function is delegated to a designated “County Recorder.”

3)  Know Who Does and Does Not Qualify For Lien Rights

Generally speaking, contractors, subcontractors, material suppliers, equipment rental companies, laborers and professionals have lien rights in Florida.  Florida does not require that you have a written contract to file a mechanics lien, so contracts can be oral, written, express or implied. However, the following do not have any rights to file a Florida mechanics lien:

  • Sub-sub-subcontractors (those hired by sub-subs)
  • Suppliers to suppliers
  • suppliers to sub-sub-subcontractors
  • Anyone who is required to be licensed in Florida, but who is not (read more about unlicensed contractor lien rights here)
  • Maintenance workers (work / materials provided must permanently improve the property)

Five Things To Know About Floridas Mechanic Lien Laws

4)  Do Not Exaggerate Your Lien Claim

This one really applies nationwide, and not just in Florida.  However, it’s particularly important in Florida, because filing a mechanics lien considered “fraudulent” is a 3rd degree felony.  The tough part is distinguishing between a “mistake” or something subject to a “good faith argument” versus an actual willful or negligent exaggeration.

Florida does not allow lien claimants to include amounts within the mechanics lien for unapproved change orders, claims and lost profits on unperformed work, and other similar legally theoretical claims for damage payments. Similarly, lien claimants should not add costs or lien fees, interest or attorney fees to their Florida mechanics lien.

While all of these amounts may be recoverable in litigation, they cannot be added to lien itself, as the mechanics lien law in Florida only allows lienors to encumber the property for the value of its actual permanent improvement to the property.  This is a typical rule all across the country, as we discussed previously in this post:  What Costs Can I Include In A Mechanics Lien?

5) Know The Foreclosure Deadline…And All Exceptions

In Florida, as elsewhere, mechanic liens are only effective for a defined period of time.  Once that time period is up, the lien expires as a matter of law unless you file a lawsuit to foreclose upon the property and the lien.  The general rule in Florida is that the lien foreclosure action is due within 1 year from the lien’s recording.

However, the 1 year foreclosure period can be shortened to as little as 60 or 20 days. It’s important to know these two exceptions:

  • Foreclosure period is reduce to 60 days if the property owner serves a Notice of Contest of Lien (F.S. 713.22(2)).
  • Foreclosure period reduced to 20 days if the owner or interested party files a lawsuit complaint and summons with a rule to show cause on the mechanics lien (F.S. 713.21(4)).

Article printed from zlien: http://www.zlien.com

URL to article: http://www.zlien.com/articles/five-things-to-know-about-floridas-mechanic-lien-laws/